File #: HCC-145-FY24    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 11/22/2023 In control: City Council
On agenda: 12/4/2023 Final action:
Title: Design of Oliver Alley Project - ARPA Funded
Sponsors: City Administrator
Indexes: Contract
Attachments: 1. Oliver Alley Design-Permit Cost Est 20231016, 2. Plan Final Concept Oliver Alley
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Submitted by: Hal Metzler

Submitting Department: Public Works

Agenda Section: Consent

 

Item Title:

title

Design of Oliver Alley Project - ARPA Funded

end

 

Suggested Action:

recommendation

I move that the Mayor and Council authorize an expenditure not to exceed $108,000 to the Low Impact Development Center for the design, engineering, and permitting of the Oliver Green Alley Project under their existing contract with the City. This expenditure is funded using American Rescue Plan Act funds as authorized by Council on November 20, 2023 and the Treasurer is authorized to make the budget modifications necessary to facilitate this expenditure.

end

 

Summary Background:

During the pandemic the City received grant funding from the Chesapeake Bay Trust to develop a concept for the renovation of the alley located North of Oliver Street between 43rd Street and Baltimore Ave (referred to as Oliver Alley) to create a pedestrian friendly green alley. This alley sees little vehicular traffic and is a main walking route from the neighborhood to Baltimore Ave, making it an ideal location for this type of project. The Low Impact Development Center (LIDC) was contracted to perform the community outreach and develop the initial concept based on feedback from the Community. Several methods of community input were utilized, including in person community meeting on site. The final concept addresses the area from 44th Ave to Baltimore Ave. The block from 43rd St to 44th Ave will be addressed in a separate stormwater project.

 

Next Steps:

Issue purchase order and begin design.

 

Fiscal Impact:

NTE $108,000

 

City Administrator Comments:

Recommend Approval

 

Community Engagement:

Several opportunities will be provided for the community to provide feedback during this process.

 

Strategic Goals:

Goal 3 - Promote a Safe and Vibrant Community

 