Submitted by: Hal Metzler
Submitting Department: Public Works
Agenda Section: Action
Item Title:
title
Completion of the University Hills Wells Blvd Green Street Project
end
Suggested Action:
recommendation
I move that the Mayor and Council authorize an expenditure not to exceed $425,000.00 to NZI Construction for the installation of the Wells Blvd Green Street and completion of the University Hills Reconstruction project under their current contract.
end
Summary Background:
In 2015 the City began a multi-year project for the reconstruction of the roads, curbs, sidewalks, and associated public infrastructure in the University Hills area of the City. As part of the project, City staff worked to incorporate Green Street elements, including the design of Wells Boulevard/Parkway as complete green street. In July 2019 the City was awarded a grant of $100,000 from the Chesapeake Bay Trust for the construction of Wells Blvd Green Street elements.
Next Steps:
Complete the University Hills project.
Fiscal Impact:
$425,000.00
City Administrator Comments:
Recommend Support
Community Engagement:
Multiple community meetings have been held on the University Hills Green Street project.
Strategic Goals:
Goal 3 - Promote a Safe and Vibrant Community
Legal Review Required?
N/A