Submitted by: Hal Metzler
Submitting Department: Public Works
Agenda Section: Consent
Item Title:
title
As Built Survey for Wells Blvd/Pkwy Green Street Project
end
Suggested Action:
recommendation
I move that the Mayor and Council authorize an expenditure not to exceed $17,000.00 to Johnson, Mirmiran, and Thompson (JMT) to complete an as-built survey for the Wells Blvd/Pkwy Green Street project as required by Prince George’s County Department of Permitting, Inspections, and Enforcement (DPIE) under their existing contract with the City.
end
Summary Background:
After several years of planning, design, and permitting the Wells Boulevard/Parkway Complete Green Street project was constructed in the Summer of 2022. A requirement of the permit as issued by Prince George’s County DPIE is that an as-built survey must be conducted and as-built drawings provided to DPIE, and if requested to Prince George’s County Department of the Environment and Department of Public Works and Transportation. This requirement was previously optional and at the discretion of the inspector, and as such was not included in the previous design and permitting proposals or authorizations.
Next Steps:
Complete As-built survey and drawings and close out permit.
Fiscal Impact:
NTE $17,000
City Administrator Comments:
Recommend Approval
Community Engagement:
A number of community meetings and other opportunities to provide comments we available over the course of the multi-year design process.
Strategic Goals:
Goal 3 - Promote a Safe and Vibrant Community
Legal Review Required?
N/A